Project Begins April 13

 

WILLMAR, Minn. – The Minnesota Department of Transportation (MnDOT) will begin the Highway 15/Main Street reconstruction project in Hutchinson on Monday, April 13, 2020. In preparation for the project start date, a temporary signal will be installed at Highway 7 and County Road 115 on Friday, April 3, 2020. The temporary signal will provide detour traffic control for the duration of the project.

Following guidance from state health officials and to prevent further spread of COVID-19, MnDOT crews will maintain social distancing practices while working.

The Hutchinson Main Street project includes the reconstruction of Highway 15 from Second Avenue North to Fifth Avenue South. This part of the project will require a detour, which goes into effect on April 13. Motorists traveling through Hutchinson will be routed on Highway 7 and County Road 115. Local traffic to homes and businesses in the downtown area will be routed on Franklin and Adams Streets. At least two intersections (Washington, Second Avenue South, and, Fifth Avenue South) will be kept open at a time for local traffic to cross Highway 15.

Included with the project, Highway 15 will be resurfaced from Fifth Avenue South to just north of the roundabout at County Road 115/Airport Road, and a northbound left-turn lane will be constructed at Linden Avenue. This part of the project will be completed under traffic. Motorists can expect temporary lane closures and short delays.

Sidewalks and pedestrian crossings will be upgraded along both project areas to make them accessible for all people.

The City of Hutchinson will replace utilities (sanitary sewer, storm sewer, and water) in downtown Hutchinson under Highway 15/Main Street during reconstruction.

Benefits of the project include:

  • Smoother road surface
  • Modern sanitary sewer and water
  • Updated city and state infrastructure
  • Upgraded sidewalks and pedestrian crossings

The state portion of the project is estimated to cost $11.5 million and to be complete by October 31, 2020. Please note that the start and end dates could change due to unforeseeable circumstances, and that all traffic impacts may not be known at this time. The contractor is R & R Excavating, Inc., of Hutchinson.

A virtual open house of the project will be available April 10-24 on the project website.
Click Here for the Project Website.

Find us on Facebook.


NEWS RELEASE

September 9, 2020

Highway 15 resurfacing in Hutchinson starts today

WILLMAR, Minn. – The resurfacing of Highway 15 from County Road 115 to Fifth Avenue South in Hutchinson starts today. Travelers will encounter temporary lane and side street closures during paving operations which are scheduled to take two weeks.

A flagging operation will direct traffic through the work zone and delays can be expected. Consider alternate routes when possible.

The resurfacing is part of the Hutchinson Main Street project which includes the reconstruction of Highway 15 from Second Avenue North to Fifth Avenue South. Also included with the project, a northbound left-turn lane will be constructed at Linden Avenue. Sidewalks and pedestrian crossings are being updated along both project areas to make them accessible for all people.

The city of Hutchinson has replaced utilities (sanitary sewer, storm sewer, and water) in downtown Hutchinson under Highway 15 during the reconstruction of Main Street.

Watch for orange cones

MnDOT asks everyone to:

  • Slow down when approaching every work zone, then navigate through with care and caution
  • Stay alert; work zones constantly change
  • Watch for workers and slow-moving equipment
  • Never enter a roadway that has been blocked with barriers or cones
  • Obey posted speed limits; fine for a work zone violation is $300
  • Minimize distractions behind the wheel and while walking or biking
  • Be patient; expect delays, especially during peak travel times

For more information, visit the project website at mndot.gov/d8/projects/hwy15downtownhutch

Find us on Facebook atwww.facebook.com/groups/MnDOTsouthwest.

 


Project Update #1Project Update #2 Project Update #3 Project Update #4 Project Update #5Project Update #6 Project Update #7 Project Update #8 Project Update #9 Project Update #10 Project Update #11 Project Update #12 Project Update #13 Project Update #14 Project Update #15 Project Update #16 Project Update #17 Project Update #18 Project Update #19 Project Update #20 Project Update # 21 Project Update #22 Project Update #23 Project Update #24 Project Update #25 Project Update #26 Project Update #27 Project Update #28 Project Update #29 Project Update #30

TwitterFacebookLinkedInEmailPrintFriendly
Translate »