2025 Street Improvement Projects

2025 Street Improvement Projects: Hassan Street SE (1st Avenue NE to Oakland Avenue SE), 3rd Ave SE (Main Street S to Hassan Street SE), 6th Ave SE (Main Street S to Hassan Street SE), 7th Ave SE (Main Street S to Hassan Street SE) Construction to begin on April 28, 2025 and is scheduled to be complete on August 1, 2025.  Stoney Point Rd SW (School Rd SW to Roberts Rd SW) and 1st Ave SE (Main Street S to Jefferson Street SE) – Construction to begin on June 9, 2025 and is scheduled to be complete on August 1, 2025.